The factory fabricates and ships a maximum of 600 tons a week of complete metal building systems. We can process up to 60 projects per week and provide load-out and delivery departure times on a schedule of up to 20 hours a day to meet driver departure requirements.

The factory can operate on a 3 shift continuous basis with weekend schedules for “surge” capacity.

Our frame manufacturing capacity of 240 tons per week utilizes three full-feature plasma cutting machines, with CNC controlled pull-thru welder, plate fabricator, and flange lines. All frames processing is linked with material handling and dispatching systems to complete the full fabrication cycle (including load and shipment) in two weeks or less.

The factory total throughput target time schedule is eight weeks.